The tunnel boring machine (TBM) for the Regional Connector project recently began its journey beneath downtown Los Angeles. The 400-foot-long TBM, known as ‘Angeli,’ will dig the twin tunnels that will connect the Expo, Gold, and Blue Lines.
The new 1.9-mile rail tunnels will be constructed using a combination of tunnel boring machine and an “open-cut” method. Angeli is responsible for 1.1 miles of tunneling between Little Tokyo and the Financial District. Already, the TBM has excavated 1,100 feet and successfully constructed 226 tunnel rings. The TBM can travel upwards of 50 feet each day and excavate 1,300 tons of soil.
Once Angeli reaches the intersection of Flower and 4th streets, the cutter head and its tail shield will be extracted and transported back to Little Tokyo, where tunneling work will begin on the second tunnel. The first tunnel is expected to be excavated by early summer, followed by the completion of the second tunnel in early 2018.
Read more about Angeli and tunnel mining on the project webpage and follow her on Twitter for weekly progress updates and the frequent musings of a two-million pound machine.
The $1.751-billion project is expected to be complete in 2021. When finished, the Connector will create two separate light rail lines — one that runs between Santa Monica and East Los Angeles and the other that runs between Azusa and Long Beach. The two lines will share five stations in downtown L.A. The new arrangement will allow for more frequent and faster light rail service and will either eliminate or reduce transfers for most riders going to and through downtown Los Angeles. The project is funded largely by the Measure R sales tax and a federal grant and loan from the Federal Transit Administration.
Categories: Projects
[…] may have seen that tunnel mining on the Regional Connector began a few weeks back. As the tunnel boring machine (known as ‘Angeli’) moves west across DTLA at […]
[…] posible que hayan visto que la excavación de túneles para el proyecto del Regional Connector empezó hace unas semanas. A medida que la máquina perforadora de túneles (TBM, conocida como […]
[…] that built the machine being used to mine the tunnels for the Regional Connector Project (video here of that TBM in action). The machines are known currently by their numbers — S986 and S987 — although a contest to […]
How are the last three blocks to 7MC going to get dug out, and exactly how do they link the construction tunnel with the existing “end-of-line” tunnel in the station?
[…] Video Of Regional Connector Tunnel Boring Underway (The Source) […]
[…] new video on The Source shows the huge machine, named Angeli, getting down to […]