Metro’s contractor Walsh/Shea Corridor Contractors (WSCC) has rescheduled the Rodeo Road two week closure to Friday, Oct. 24.
The full street closure is needed to complete the underground perimeter wall with steel piles for the Crenshaw/Expo station box. The work schedule and the detours remains the same.
Originally rescheduled for Friday, Oct. 3, the two-week full street closure of Rodeo Road at Crenshaw Boulevard will precede excavation of the underground station. Nightly closures are taking place in this location from 9 p.m. to 6 a.m. the next day as crews continue to work on storm drains and utilities in the area.
This location is of vital importance for the project since this is where the tunnel boring machines will be lowered to begin digging the southbound tunnel through Crenshaw/MLK station and finalize the Crenshaw/Vernon station. The lowering of the tunnel boring machine is expected to take place next year.
Categories: Projects
I am hoping that there will be an underground passage way at the Crenshaw/Expo station to enable hassle-free transfers between the Crenshaw and Expo lines. [This would be similar to the passage way at the North Hollywood station.]