Here is the news release from the Gold Line Foothill Extension Construction Authority, the agency building the 11.5-mile addition to the Gold Line between eastern Pasadena and the Azusa/Glendora border. Yep, it’s another project funded by Measure R:
Four-Day Full Closure of Huntington Dr & Second Ave Intersection Begins Friday Morning, August 8; Followed by Six Weeks of Nighttime Directional Closures
WHO: Residents / Commuters / Businesses in the Cities of Arcadia.
WHAT: Crews will be performing two phases of work on the light rail bridge structure over the intersection of Huntington Dr and Second Ave in the City of Arcadia. This work is part of the 11.5-mile Metro Gold Line Foothill Extension light rail project. The first phase of work will require a full closure of the intersection to thru-traffic for four days, beginning Friday morning, August 8, to allow crews to install the bridge girders.
Following the four-day full intersection closure, six weeks of nighttime directional closures will begin on Tuesday night, August 12, Sundays thru Thursdays ONLY, from 8 p.m. to 6 a.m. Huntington Dr will be closed to thru-traffic in one direction at Second Ave (either eastbound or westbound; never concurrently), while no thru-traffic will be allowed on Second Ave at Huntington Dr. The directional closures are needed to install the cross beams and deck steel onto the light rail bridge structure.
During these closures, detours and signage will be posted to guide motorists and pedestrians around the work area. Access to all local businesses, including those on Huntington Dr and Second Ave, will remain available.
WHEN:
– Full Closure:
Friday morning, August 8, 2014 at 12:00 a.m. thru Tuesday, August 12, 2014 at 6:00 a.m.: The intersection of Huntington Dr and Second Ave will be fully closed to thru-traffic to install the bridge girders. Traffic will be detoured and signage will be posted to direct motorists and pedestrians (see detour map above).
– Directional (One-Way) Nighttime Closures:
Beginning Tuesday night, August 12, 2014 for approximately six weeks, Sundays thru Thursdays ONLY, from 8:00 p.m. to 6:00 a.m.: Huntington Dr will be closed to thru-traffic at Second Ave in one direction (either eastbound or westbound; never concurrently), while no thru-traffic will be allowed on Second Ave at Huntington Dr. These closures are to install the cross beams and deck steel. Traffic will be detoured and signage will be posted to direct motorists and pedestrians during these hours. No work will be performed on Fridays or Saturdays.
WHERE: Intersection of Huntington Dr and Second Ave in the City of Arcadia.
WHAT TO EXPECT:
•Detour routes will be in place during the closures and signage will be posted to direct motorists and pedestrians.
•Access to all local businesses, including those on Huntington Dr and Second Ave, will remain available at all times during the construction.
•Bus stops in this vicinity may be temporarily relocated. For information about:
•Foothill Transit bus services call (800) RIDE-INFO (800-743-3463) or go to www.foothilltransit.org
FOR MORE INFORMATION
– Visit www.foothillgoldline.org
# # #
About the Metro Gold Line Foothill Extension Construction Authority: The Construction Authority is an independent transportation planning and construction agency created in 1998 by the California State Legislature. Its purpose is to extend the Metro Gold Line light rail line from Union Station to Montclair, along the foothills of the San Gabriel Valley. The Construction Authority built the initial segment between Union Station and Pasadena and is underway on the Foothill Extension. The Foothill Extension (now known as the Foothill Gold Line) is a nearly $2 billion extension that will connect Pasadena to Montclair in two construction segments – Pasadena to Azusa and Azusa to Montclair. The 11.5-mile Pasadena to Azusa segment is on time and on budget, and will be completed in late-September 2015 when it will be turned over to Metro for testing and pre-revenue service. It is fully funded by LA County’s Measure R. Metro will determine when the line will open for passenger service. Three design-build contracts, totaling more than $550 million, are being overseen by the Construction Authority to complete the Pasadena to Azusa segment. The Azusa to Montclair segment is environmentally cleared and is undergoing advanced engineering and design. It will be shovel-ready for a design-build contract in 2017. The $1 billion segment is currently unfunded for construction.