Roadway reconstruction on Sepulveda Blvd between Montana Ave and Church Ln planned March 14 – April 28

Here’s the press release from Metro:

The I-405 Sepulveda Pass Improvements Project contractor is scheduled to conduct roadway reconstruction work of approximately one-half mile of Sepulveda Boulevard in West Los Angeles between Montana Avenue and Church Lane between March 14 and April 28, 2014. The contractor will perform a full-depth reconstruction of this portion of Sepulveda Boulevard, demolishing existing asphalt concrete, grading, compacting and paving new roadway.  This work will require daytime lane reductions and full night-time and weekend street closures in this area.

The work schedule is as follows:

Sepulveda Boulevard Closures from Montana Avenue to Church Lane:

Full weekend closures: from 10 p.m. on Fridays to 6 a.m. on Mondays, March 14 to April 28.

Reduced to One Lane in Each Direction: from 6 a.m. to 10 p.m., Mondays to Fridays, March 14 to April 28.

Full nighttime closures: 10 p.m. to 6 a.m. on weekday nights, March 17 to April 28.

Detours:  Night & Weekend Closures:

Southbound Sepulveda, right to westbound/southbound Church Lane, left to eastbound Montana, right to southbound Sepulveda.

Northbound Sepulveda, left to westbound Montana Avenue, right to northbound/eastbound Church Lane, left to northbound Sepulveda.

What to expect:

2 replies

  1. Going south on Veteran, I regularly take a left/west on Montana @ Gayley and then continue on Montana thru Sepulveda and under the bridge to Church Lane. IS MONTANA OPEN UNDER THE 405 BRIDGE TO CHURCH LANE. your info is very unclear!!!

    • Hi Mary,

      As far as I can tell, the construction work takes place on Sepulveda. Montana is open and listed as a detour option.

      Anna Chen
      Writer, The Source