Grinding and saw-cutting work is planned for the I-405 Sepulveda Pass Widening Project March 5 through 12. Metro’s contractor will be shaving and leveling out the road pavement on the right-hand shoulder of the freeway between Getty Center Drive and Ventura Boulevard in phases. Some ramp and lane closures are planned. Details from the construction notice follow:
What: Freeway lane and ramp closures to perform saw-cutting and grinding work activity.
When: Night-time work activities for the two right freeway lane and ramp closures on the northbound and southbound I-405 freeway will continue and is anticipated to last for approximately three more weeks, weather permitting. Lane and ramp closures will be from 10:00pm to 6:00am, with the freeway open to thru traffic.
Where: San Diego Freeway (I-405) between the Santa Monica Freeway (I-10) and the Ventura Freeway (US- 101). Saw-cutting and grinding work activities will be conducted in segments along the I-405 freeway. Freeway segments for the upcoming weeks are scheduled as follows:
Freeway Segments Anticipated Dates of Work Activity Duration Northbound I-405, Getty Center Drive to Skirball March 5, 8, and 9 3 Nights Northbound I-405, Skirball to Ventura Blvd. March 10, 11, and 12 3 Nights
What to expect:
- Ramp and lane closures will be coordinated with Caltrans. Detour signs will be posted where ramp closures occur.
- There will be the same number of thru traffic lanes as there are currently at the completion of this activity.
- The saw-cut and grind work activity is being conducted in addition to the on-going full freeway closures and lane re-striping work activities on the I-405. For information regarding freeway lane re-striping work and the corresponding full freeway closures, please visit www.metro.net/I-405.
For road side assistance during construction, please call the Metro Freeway Service Patrol at #399.