Street work begins Monday that will impact bus service and crosswalks at Blue Line’s Artesia Station

Beginning Monday, Feb. 4, the roadway buses operate on in the Artesia Blue Line Station will be reconstructed and a water line under the roadway will be replaced. The project will be completed in seven phases, and is expected to take approximately 90 days to complete, weather permitting.

The station will remain open to the public throughout the duration of construction. However, the work will involve moving bus stops at times, as different portions of the roadway will be repaved during the various phases of the project.

In addition, the existing crosswalk between the parking lot and the station/bus stops will be temporarily relocated during construction. Most of the construction work will be done on weekdays, during the daylight hours, with occasional night and weekend work as needed. Phase 5 and 6 of this project will take place on weekends. The work done in each of the construction phases is described below, after the jump.